The tentative schedule is as follows:
- February 2021: Council approved conceptual layout and design of bathrooms, changing rooms, sand showers. Instructed Shawn to present this concept to the DNR
- May 2021: City will present conceptual layout and design to DNR in Brunswick. Will take DNR comments and incorporate into final layout and have them publish it for public comment
- June/July 2021: DNR advertises and solicits public comment
- July/August 2021: City finalizes design and send it to Planning Commission
- August/September 2021: City Council accepts and approves Planning Commission comments
- September/October 2021: City bids project and project is awarded
- November/December 2021: Construction starts
- April/May 2022: Construction Completed and bathrooms, changing rooms, and showers opened to public.